PMP Questions 51-60

pmp exam questions
Photo by Teona Swift on Pexels.com

PMP Question 51

At a critical milestone in a development project, it is determined that implementation is two months behind schedule. The project manager is concerned that the root cause is lack of conformance to requirements in the design of the new billing system. More extensive measurements are taken to see if this is, in fact, the problem. Those measurements are:

Member Content

Explanation about the question:


PMP Question 52

Which of them is the act of adding detail, order, and size to items in the Product Backlog?

Member Content

Explanation about the question:

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 53

How much time should the Product Owner dedicate to managing the Product Backlog?

Member Content

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Explanation about the question:

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 54

Which technique allows large numbers of ideas to be sorted into groups for review and analysis?

Member Content

Explanation about the question:

The Options

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


PMP Question 55

According to the Agile Manifesto, which of the following describes the more valued items?

Member Content

Explanation about the question:


PMP Question 56

You’ve been appointed as the new project manager for a critical project that is already underway. Upon reviewing the project’s progress, you discover that not only is the project significantly behind schedule, but also that the budget has been exceeded by 30%. Furthermore, you find evidence suggesting that key project requirements were misunderstood in the initial planning phase, leading to a substantial rework effort.

Despite these challenges, the previous project manager has consistently reported to the sponsor that the project is progressing smoothly and is on track to meet its objectives. What is the MOST appropriate course of action for you to take?

Member Content

Explanation about the question:


PMP Question 57

Which of the following is the best reason that PMI publishes a Code of Ethics?

Member Content

Explanation about the question:


PMP Question 58

You have just assigned as a project manager with core team members. You asked your members to work on the process of defining stakeholders to create a model  with multiple dimensions that improves the depiction of the stakeholder community. They started to discuss about the technique that they should use to create the model. Which technique is the best to create this model?

Member Content

Explanation about the question:


PMP Question 59

If resource planning is done at an early stage, what is the latest point at which resource assignments are usually confirmed and start and finish dates are usually established?

Member Content

Explanation about the question:


PMP Question 60

During a software development project, a project stakeholder expresses repeated concerns about a specific feature developed by the team, stating that it does not align with the original design specifications. Despite several clarifications from the development team, the stakeholder remains unsatisfied and insists that the feature is not meeting the intended requirements. How should the project manager address this issue to ensure alignment with the project scope?

Member Content

Explanation about the question:

PMP Question 41-50

Question 41

Who is accountable for the Product Backlog when it comes to content and order?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 42

A customer is requiring a minor scope change and expects you to do this without delays and additional costs. You believe that you have adequate authorization to make the decision by yourself, but you are not quite sure. What should be your next steps?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 43

In the middle of the project, your project sponsor has asked you, “What do we expect the total project cost, now?” Which of them should you use to answer?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 44

Which of the following qualities should a project manager prioritize when assessing the consistency and reproducibility of repeated measurements or actions within a project?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 45

David is a project manager working for a prominent book publishing company. As the most senior project manager within the organization, he often gets paired with strong- willed project sponsors. During a recent project meeting, David’s project sponsor began yelling in frustration at the project’s status, which was blocked because of a critical resource being out ill. In frustration, the sponsor began spewing profanities at David, questioning his ability to manage effectively. In response, David calmly assured the project sponsor that a contingency plan would be implemented and requested that they speak privately to address his frustrations. David then excused the rest of the project team. What core value did David uphold during the meeting?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 46

You took over a new project. The previous project manager completed some of the WBS. When you begin to define the project activities, you realize that the WBS work packages expected to occur in the next year are planned in detail, but the work packages for later in the future are not planned with much detail, if any detail at all. You determine:

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 47

A new regulation requires consumer warnings on labels, but a company’s product package is too small to fit the added information. The regulatory specification does not provide a solution, so the agile team decides to solve the problem by displaying the information on a fold-out flap. The start of mass production of the new labels, the project’s next milestone, is scheduled to begin in five days. What should the agile team do next?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 48

In which of the following methods of resolving conflict, will the conflict typically reappear again?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Question 49

You are very interested in becoming a project manager. You have been mentored with other experienced project managers in your organization to learn more about how to be an effective project manager. You’ve been told your organizational skills and communication skills are excellent. However, you need some additional training in accounting and budgeting skills, because you are weak in these general management areas. The mentor who was honest enough to tell you this explained it which of the following ways?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 50

A project manager is preparing to send five engineers to Japan to install a high-security network. The engineers have never been outside of the United States before. Prior to their travel, the project manager asks the Japan-based manager to give the engineers an overview of their history, customs, and social norms. What is the primary objective of the project manager in this situation?

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

PMP Questions 31-40

Photo by Damir on Pexels.com

Question 31

In managing rates and resource assignments in an Agile virtual team, what principle should guide the project manager’s approach?

A) Prioritizing the allocation of high-cost resources to the most complex tasks, under the assumption that a higher rate is a direct indicator of a resource’s ability to handle complexity and deliver high-quality outcomes.

B) Focusing on minimizing the use of external resources to reduce overall project costs, even if it means compromising on the breadth of skills or experience available to the project, under the assumption that internal resources always provide better value.

C) Balancing the cost of resources with the value they bring to the project, considering their skills, experience, and the strategic importance of their contributions, to ensure an optimal return on investment and project success.

D) Assigning resources primarily based on their geographic proximity to the majority of the team or the project stakeholders, to facilitate easier coordination and potentially reduce costs associated with time zone differences.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 32

During a project, your Agile team realizes that the workload is unevenly distributed, with some members feeling overwhelmed while others are underutilized. What Agile technique should you use to rebalance the team workload effectively?

A) Redefine team roles and responsibilities to match the current workload without consulting the team.

B) Implement a strict task assignment system to evenly distribute tasks among team members.

C) Encourage team members to work overtime to complete their tasks faster.

D) Conduct a Retrospective meeting to discuss workload balance and collaboratively find solutions.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 33

Your Agile team is diverse, with members speaking multiple languages, which has led to some communication challenges. What strategy should you adopt to improve communication and ensure project success?

A) Implement daily stand-ups to encourage regular communication and identify any misunderstandings early.

B) Require all team members to communicate only in the most common language.

C) Use only written communication to avoid language barriers.

D) Assign a translator to the team to facilitate communication during meetings.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 34

What is the primary advantage of leveraging technology solutions to facilitate face-to-face communication in virtual teams following a predictive approach?

A) Significantly reducing the reliance on traditional project documentation by shifting most of the project communications and updates to live video calls, thereby streamlining the information dissemination process.

B) Potentially increasing the project’s overall budget due to the costs associated with implementing state-of-the-art video conferencing tools and technologies, which, while expensive, are deemed necessary for enhancing team interaction.

C) Enhancing team cohesion and understanding through improved interpersonal communication, as face-to-face interactions, even if virtual, help in building relationships and clarifying complex project issues more effectively than text-based communications.

D) Simplifying the entire process for submitting and approving change requests by discussing them in real-time during video calls, thus avoiding the bureaucratic paperwork typically involved in predictive project environments.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Question 35

In a predictive project environment, what is the best strategy for assigning responsibilities within a newly formed virtual team?

A) Employing a random task assignment strategy to push team members out of their comfort zones, encouraging them to learn new skills and adapt quickly to unforeseen project challenges, thus fostering a versatile and resilient team.

B) Centralizing decision-making by delegating all critical and complex tasks exclusively to the most senior team members, assuming their experience guarantees the highest quality of work and adherence to project timelines.

C) Allowing team members to select their tasks purely based on personal preference, fostering a democratic and inclusive atmosphere that values individual choice over project needs or strategic fit.

D) Determine assignments based on a detailed assessment of each member’s experience, knowledge, skills, and attitude, ensuring that tasks are aligned with individual strengths and project requirements for maximum efficiency.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 36

What is the key benefit of using information radiators in an Agile virtual team?

A) Completely eliminating the need for daily stand-up meetings by providing an always-up-to-date digital dashboard that tracks project progress, thereby freeing up more time for development activities.

B) Increasing transparency and offering quick access to vital project information, such as current sprint progress and existing impediments, thus fostering a culture of openness and continuous improvement across the team.

C) Serving as the sole basis for evaluating team performance and individual contributions, thereby simplifying the appraisal process by focusing on quantifiable metrics displayed on the information radiator.

D) Replacing traditional digital communication tools with physical, highly visible boards placed in common areas of the virtual workspace, to ensure that every team member has uninterrupted access to project updates.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Question 37

You have recently been appointed as the project manager for a new city park development project. The project will not only include playgrounds and walking paths but also a small amphitheater for community events.

In the early stages of this project, who among the following should you prioritize as a key stakeholder to engage with?

A. Local government regulatory bodies, essential for ensuring compliance with local laws and regulations, their early involvement can significantly impact project approvals and progression.

B. Playground equipment suppliers, crucial for sourcing materials, but their engagement is more tactical and can be addressed in later project phases.

C. Internal financial analysts of your organization, important for budgeting and financial planning, but their role is often more internal and less critical in the initial stages.

D. Media outlets for publicity of the project, important for public relations, but their involvement is not critical in the early stages of project planning.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 38

In the context of team building, why is it important to evaluate a team holistically?

A) To exclusively focus on the strengths of the team, disregarding potential areas for improvement.

B) To understand team dynamics, including strengths, weaknesses, and preferences, without considering how these factors interplay.

C) Because it is a standard procedure in all project management methodologies, overlooking the specific needs of individual teams.

D) To identify team members to be removed from the project, solely based on their perceived weaknesses.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Question 39

In a project team working on a new product launch, a disagreement arises between the marketing and engineering teams about the product’s features. The marketing team wants advanced features for better market appeal, while the engineering team is concerned about the feasibility and time constraints of these features.

Which option below best represents the role of conflict management?

A) Ignoring conflicts to maintain project harmony.

B) Addressing conflicts before they escalate.

C) Letting conflicts resolve themselves.

D) Concentrating solely on the technical aspects of conflicts.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 40

In a project with a multicultural team, communication issues have arisen due to language barriers and cultural misunderstandings. As the project manager, you aim to address these challenges. Which of the following strategies would be least effective in improving team cohesion and performance?

A) Implementing regular cross-cultural training sessions focused on improving communication and understanding among team members.

B) Creating a mentorship program pairing team members from different cultural backgrounds to promote mutual understanding and collaboration.

C) Establishing a communication protocol that includes regular check-ins and feedback sessions to address and resolve cultural misunderstandings promptly.

D) Hiring a professional translator to assist with communication between team members who do not share a common language.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

PMP Questions 21-30

Photo by Ulrick Trappschuh on Pexels.com

Question 21

The project you’re managing involves collaboration between teams from two different companies with distinct corporate cultures. To unify the teams, you recognize the need to establish common team norms. What approach do you take to establish effective team norms for this collaborative project?

A) Holding a joint workshop where team members from both companies can contribute to the creation of shared norms, ensuring buy-in from all participants.

B) Drafting a set of norms based on your company’s culture and enforcing them across the combined team to maintain consistency.

C) Allowing each company to follow its own set of norms to avoid conflict, relying on project milestones to keep the teams aligned.

D) Deciding that establishing team norms is too time-consuming and unnecessary, focusing instead on individual accountability for project deliverables.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 22

During the procurement process, the project manager notices that the supplier is unwilling to agree on specific quality requirements. What should be the project manager’s next step?A) Continue with the procurement process despite the supplier’s unwillingness to agree on specific quality requirements, potentially compromising the project’s quality standards but avoiding delays in the procurement timeline

B) Seek intervention from senior management to leverage their authority and experience in negotiating with the supplier, possibly leading to a resolution that upholds the project’s quality requirements.

C) Engage in further negotiations to explore alternative terms, such as price adjustments or additional services, that could offset the impact of not meeting the specified quality requirements.

D) Collaborate with the project team to generate creative solutions or identify alternative suppliers who can meet the quality requirements, ensuring the project’s standards are maintained.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 23

A project manager is overseeing a project where the external vendor has consistently failed to meet the SLA terms. What should be the project manager’s immediate action?

A) Consider ending the contractual relationship with the vendor due to their consistent failure to meet the SLA terms, potentially seeking a new vendor who can better fulfill the service expectations.

B) Initiate discussions with the vendor to renegotiate the SLA terms, aiming for more realistic expectations or improved service levels that the vendor can consistently meet.

C) Record the instances where the vendor failed to meet the SLA terms and engage in a constructive dialogue to identify the root causes and collaboratively develop a plan to prevent future failures.

D) Choose not to address the minor SLA breaches, focusing instead on more critical aspects of the project, as long as the overall project progress and outcomes are not significantly affected.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 24

The project manager is using the MoSCoW technique for prioritization. Suddenly, a stakeholder demands that a ‘Could Have’ feature be upgraded to ‘Must Have.’ How should the project manager handle this situation?

A) Promptly reclassify the ‘Could Have’ feature to ‘Must Have’ based on the stakeholder’s demand, potentially impacting the project scope and resource allocation.

B) Conduct a thorough analysis of how the change in prioritization will affect the project’s scope, timeline, and budget, ensuring that any decision made is informed and balanced.

C) Decline the stakeholder’s request to maintain the original prioritization, emphasizing the importance of adhering to the established project plan and priorities.

D) Seek input from other stakeholders to gauge their perspectives on the proposed change in prioritization, ensuring that the decision is well-rounded and considers multiple viewpoints.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 25

The project’s performance report shows a significant deviation in actual costs from the planned budget. What should be the project manager’s first course of action?

A) Revise the project budget to accommodate the higher actual costs, ensuring that the project remains financially viable while addressing the cost overruns.

B) Conduct a detailed analysis to identify why the actual costs deviated from the planned budget and take appropriate corrective measures to prevent similar discrepancies in the future.

C) Communicate the cost overrun to the stakeholders and seek additional funding to cover the unexpected expenses, ensuring that the project can continue without financial constraints.

D) Consider scaling back the project scope to reduce costs, ensuring that the project stays within the original budget while still achieving its core objectives.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Question 26

After a sprint, the team realizes that their communication practices were ineffective. What should the team do next?

A) Persist with the existing communication practices despite their identified inefficiencies, potentially leading to continued miscommunications but avoiding the disruption of changing practices mid-sprint.

B) Attribute the communication practices’ ineffectiveness to the team members’ failure to adhere to them, overlooking the possibility that the practices themselves might be flawed or inadequate.

C) Choose not to address the communication practices’ shortcomings, fearing that changes might lead to confusion among team members, even though this might result in ongoing communication challenges.

D) Update their communication practices incorporating the insights gained from the sprint’s experiences, aiming to enhance the effectiveness of communication in the subsequent sprints.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 27

In an agile project, the customer wants to add new features to the product backlog, which will impact the agreed performance levels. How should the team approach this situation?

A) Politely decline the customer’s request, emphasizing the importance of sticking to the original project scope to ensure timely delivery and avoid unnecessary complications.

B) Accept the new features but inform the customer that additional resources or time will be required, presenting a clear plan for how the team will accommodate these changes.

C) Conduct a thorough analysis of the new features to determine their impact on the project’s performance levels and overall objectives, and then negotiate a compromise with the customer.

D) Immediately incorporate the new features into the project backlog, reassessing the project’s performance levels and resource allocation to accommodate these changes without compromising project integrity.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 28

A key team member is unexpectedly unavailable due to personal reasons. How should the project manager handle the situation to minimize the impact on the project schedule?

A) Pause or delay the tasks assigned to the unavailable team member until they return, potentially impacting the project timeline but maintaining the original team structure.

B) Distribute the tasks of the unavailable team member among other team members, which may lead to increased workload and potential burnout but keeps the project on schedule.

C) Revise the resource calendar to reflect the team member’s unavailability, explore options for alternative resources, or adjust the project schedule to accommodate the change without compromising the project’s progress.

D) Implement a risk response plan to address the unavailability of the team member, focusing on proactive measures to mitigate potential delays and maintain project momentum without disrupting the existing team dynamics.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 29

A project manager in a luggage manufacturing company needs to explore new business opportunities and present three proofs of concepts (POCs) to the executive team. Sales are declining rapidly, putting the company’s future at risk. The project team consists of 15 stakeholders from various parts of the organization, selected for their independent thinking. They have differing opinions on the best opportunities, leading to frequent disagreements.

To address the diverse viewpoints, the project manager opts for an agile approach to quickly establish a shared understanding and identify the most promising solutions to present to the executive team. Which two approaches should the project manager consider? (Choose two)

A) Educate stakeholders on creating user stories and story maps to share their ideas with the group and collectively select the top three for developing the POCs.

B) Oversee the work while empowering three agile teams, each comprising five members, to self-organize and brainstorm new business concepts as user stories. These stories will be reviewed at retrospectives and developed iteratively.

C) Distribute a survey to the 15 stakeholders soliciting new business ideas and concepts. Anonymously share all responses and vote on the three most favored ideas.

D) Give priority to the ideas of executive or senior stakeholders. Empower them as team leads of self-organizing agile teams responsible for delivering POCs to the company incrementally.

E) Require each stakeholder to craft a vision statement and use an Extreme Programming (XP) metaphor to explain their best idea. After all stakeholders vote for the top three ideas, develop them as POCs.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

Question 30

A project will create digital keys for 18,500 employees at an airport. The project management plan states that security clearance data for employees must be verified and updated in a digital security file every 6 months. This is part of the acceptance criteria. In month 3, the project manager discovers that the company hired to maintain the digital security files has filed for bankruptcy.

Which statement describes the status of this project?

A)This project will fail.

B) This project has an issue.

C) This project is noncompliant.

D) This project is high risk.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

PMP Questions 16-20

Question 16

When managing a virtual team in a predictive project environment, what is the most critical factor to consider for ensuring effective communication across different time zones?

A) Utilizing asynchronous communication tools and establishing a 24-hour response policy to accommodate diverse time zones while ensuring timely progress updates and feedback.

B) Implementing a mandatory policy that requires all team members to work during a specific overlap of hours, regardless of their local time, to foster real-time collaboration and immediate feedback.

C) Organizing daily mandatory video conferencing meetings for all team members to simulate a traditional office environment and enhance team cohesion, despite the inconvenience to some team members due to their local time zones.

D) Strategically assigning tasks based on the geographical proximity of team members to the project manager’s time zone to simplify scheduling and reduce the complexity of managing across multiple time zones.

Become a Member

Question 17

You’re leading a new project to develop an innovative software application. The team comprises members from different departments, each bringing unique skills and experiences. To ensure everyone is aligned from the outset, you decide to create a Team Charter. What is the primary focus when drafting the Team Charter for your project team?

A) Listing the technical specifications of the software application to ensure all developers understand the project requirements.

B) Outlining each team member’s daily tasks for the first month to kickstart the project with clear direction.

C) Establishing shared values, communication guidelines, and conflict resolution methods to foster a collaborative team environment.

D) Documenting a detailed project timeline, including milestones and deadlines, to track project progress effectively.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 18

Halfway through the project, a significant client request necessitates a shift in project priorities. This change could impact the timeline and resource allocation. You schedule a meeting with key stakeholders and team leads to discuss the way forward. In negotiating the shift in project priorities, what principle should guide your approach?

A) Insisting on the original plan to avoid setting a precedent for client-driven changes, maintaining project scope and deadlines.

B) Focusing solely on the additional revenue the change request brings, prioritizing any tasks that increase project budget.

C) Automatically accepting the client’s request, reallocating resources to new priorities without reviewing the impact on the project’s original goals.

D) Balancing the client’s needs with the project’s scope and resources, seeking a compromise that aligns with team capabilities and project goals.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 19

Two team members have a disagreement over the best approach to a critical component of the project. Their conflict has begun to affect the morale of the entire team, and delays are imminent if a resolution is not found. As the project manager, how do you facilitate conflict resolution between these team members?

A) Organizing a mediation session where both parties can present their viewpoints, followed by a discussion to find a mutually acceptable solution.

B) Letting them resolve it on their own to foster independence, avoiding any managerial intervention that could stifle team dynamics.

C) Deciding the outcome yourself based on your understanding of the project needs, to expedite resolution and minimize project delays.

D) Encouraging a team vote on the disputed approaches, going with the majority to ensure team cohesion and democratic decision-making.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.


Question 20

Your project team is distributed across multiple time zones, which has led to communication challenges. Important messages are getting lost, and team members feel disconnected from the project’s progress. How do you establish effective communication protocols for your distributed project team?

A) Implementing a 24/7 chat room where team members can drop messages, expecting immediate responses regardless of time zones.

B) Setting up a weekly all-hands meeting at a time that’s only convenient for the headquarters, summarizing project updates.

C) Creating a structured communication plan that includes regular updates, asynchronous communication tools, and scheduled meetings accommodating all time zones.

D) Relying solely on email for all communications, assuming it’s the most straightforward way to keep everyone informed on their own time.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

PMP Questions Service

Photo by Ketut Subiyanto on Pexels.com

Hello everyone,

I have an exciting announcement to share with you today. I’ve been PMP certified since 2004 and have been conducting PMP preparation training for 20 years. Alongside, I’ve worked as a consultant on many projects, giving me a deep understanding of the skills tested in the PMP exam. Leveraging my training and consulting experiences, I’ve started sharing PMP questions on my blog.

With my PMP Questions Service, you can now manage your PMP exam preparation process more effectively and efficiently. For just $19 per month, ($209 per year) you’ll gain access to both current and future PMP exam questions. Each question is accompanied by explanations for both correct and incorrect answers, as well as additional topic explanations related to that question. This allows you to prepare comprehensively for the PMP exam.

Why should you choose my PMP Questions Service?

  • Effective Preparation: Practice with questions that simulate the real exam format to enhance your exam strategy.
  • Detailed Explanations: Each question comes with explanations for both correct and incorrect answers, as well as additional topic explanations.
  • Save Time: Improve your time management skills while solving questions.
  • Up-to-date Content: Keep testing yourself with new and current questions every month.

To benefit from my service, simply visit any PMP Question titled content to sign up. Remember, using the right resources is crucial for a successful exam experience. Stay ahead with my PMP Questions Service!

Have questions? Feel free to reach out. I’m here to help.

Wishing you success,

Gökrem Tekir

PMP Questions 11-15

Photo by Artem Podrez on Pexels.com

Question 11

Which of the following best describes the role of conflict management in project management?

A) Avoiding any conflicts to ensure a smooth project progression.

B) Intervening before a negative outcome of a conflict occurs.

C) Allowing conflicts to resolve naturally without intervention.

D) Focusing solely on the technical aspects of conflicts.

Become a Member For The Answer


Question 12

Your Agile team is working on a software development project. The team has identified a new technology that could significantly enhance the project outcome but requires specialized knowledge that the current team lacks. What Agile practice should you implement to address this gap?

A) Increase the frequency of Sprint Reviews to monitor progress more closely.

B) Allocate additional budget to hire an external consultant with expertise in the technology.

C) Engage in a Spike to research the new technology and gain the necessary knowledge.

D) Immediately enroll team members in training sessions, pausing the project until training is completed.

Become a Member For The Answer


Question 13

Your project requires specialized knowledge in a new technology that only a few team members are familiar with. To ensure the project’s success, you need to strategize the team’s composition from the start. What method will you use, and how does it contribute to the project?

A) The Delphi Technique, soliciting expert opinions through questionnaires to make informed decisions about team composition based on consensus.

B) The pre-assignment method, assigning team members based on their specific skills and the project’s needs. This ensures that individuals with the necessary expertise are involved from the beginning, contributing to the project’s efficiency.

C) Utilizing a Skills Inventory Database to passively match team members to tasks based on their listed skills, hoping to cover all necessary areas.

D) Implementing a democratic team selection process, where team members vote on their preferred roles and tasks, promoting engagement but potentially overlooking skill mismatches.

Become a Member For The Answer


Question 14

Towards the end of a critical project phase, you realize that the utilization of physical resources has not been as efficient as planned, leading to potential delays and cost overruns. What action will you take to better manage these resources and mitigate the impact on the project?

A) Revising the project schedule to extend deadlines, accommodating the inefficiencies without directly addressing the underlying resource management issues.

B) Tighten resource monitoring and reward efficient use to improve management and prevent project delays.

C) Outsourcing part of the work to external vendors, transferring the responsibility for resource management to a third party.

D) Conducting a series of workshops on resource management for the team, hoping to improve future resource utilization through education alone.

Become a Member For The Answer


PMP Question 15

An Agile team is working on a project with a tight deadline. Halfway through, they realize some of the technologies they are using are outdated and causing delays. What should the team do to address this issue without compromising the project timeline?

A) Continue with the current technologies to avoid further delays caused by the learning curve of new technologies.

B) Wait until the project is completed before exploring new technologies for future projects.

C) Immediately switch to the latest technologies without assessing their impact on the project.

D) Organize a Lean Coffee meeting to discuss and prioritize the adoption of new technologies.

Become a Member For The Answer

PMP Question 10

Why is contingency planning crucial in resource management?

A) To minimize project costs by adhering strictly to the budget.

B) To provide a safety net for team members, ensuring they are not held accountable for mistakes.

C) To reactively respond to risks as they arise, minimizing their impact on the project.

D) To align project goals with corporate policies, ensuring organizational strategies are met.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

PMP Question 9

What primary advantage does consistent training and skill enhancement offer in project management?

A) Maintains team flexibility to accommodate evolving project demands and technological progress, thereby sustaining project efficiency and ensuring that the team remains agile in responding to changes.

B) Guarantees adherence to the most current industry standards and regulatory mandates, ensuring that the project stays compliant with evolving requirements and best practices.

C) Mainly aims to decrease the project’s dependence on external training provisions by building an internal knowledge base and expertise within the team, reducing the need for costly external training resources.

D) Enhances project implementation by establishing uniform skills and methodologies throughout the team, which leads to improved communication, collaboration, and overall project execution.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.

PMP Question 8

In the context of effective resource management planning, why is it crucial to maintain a pool of external resources such as freelancers or consultants?

A) It fosters a continuous influx of innovative ideas and diverse perspectives, enhancing the project’s creativity and adaptability.

B) External resources often possess specialized skills and expertise, making them more adept at handling intricate project tasks with efficiency.

C) Utilizing external resources tends to be a more financially prudent approach than investing in training existing staff for transient or specialized roles.

D) They serve as a reliable contingency plan, providing supplementary support during periods of heightened workloads or unforeseen resource scarcities, thereby ensuring uninterrupted project progression.

Erişim elde etmek için abone olun

Buna benzer içerikleri daha fazla okumak için bugün abone olun.